What goes in the "Task" column in Project Forecast Writeback sheet?

Hello!

I am trying to perform a project forecast writeback using the Project Forecast Worksheet. Below is the error message I am getting when I try performing writeback, basically saying my project task cannot be found. My question is, what goes in the “Task” column in excel? Is it the TaskID or TaskCD in Acumatica?

Thanks!

Hi Julie,

Task would be the task code of your project, in your case it looks like “SUPPORT”. You can find the list of tasks from the “Tasks” tab of the Projects screen:

Also, I would like to highlight that you seem to be trying to writeback to project “X” – this is the non-project code, and I don’t believe Acumatica allows you to create a project forecast for project “X”.

Thank you Gabriel, that was helpful to know!